Court of Federal Claims Adopts Broad View of its OT Bid Protest Jurisdiction

In a recent decision, Blue Water Autonomy, Inc. v. United States, the U.S. Court of Federal Claims (“COFC” or the “Court”) weighed in on ongoing debate over the Court’s jurisdiction to hear protests regarding other transaction (“OT”) agreements.  Nos. 26-396, 26-944 (Fed. Cl. Oct. 29, 2026).

As a reminder, under the Department of Defense's ("DoD") OT authority, DoD agencies are permitted to enter into OT agreements, which are legal instruments, other than procurement contracts, cooperative agreements, or grants, pursuant to the authority delegated to the Secretary of Defense and the Secretaries of each military department under 10 U.S.C. § 4021.  OT agreements are not required to comply with the federal regulations, such as the FAR, that apply to standard procurement contracts.  Building on section 4021, 10 U.S.C. § 4022 permits DoD to carry out prototype projects “directly relevant to enhancing the mission effectiveness of personnel of the [DoD] or improving platforms, systems, components, or materials proposed to be acquired or developed by the [DoD]” using OT agreements.

Given the exemption from typical procurement rules, there has been an open question as to whether OTs are subject to the Court’s bid protest jurisdiction under the Tucker Act, which confers COFC with “jurisdiction to render judgment on an action by an interested party objecting to . . . the award of a contract or any alleged violation of statute or regulation in connection with a procurement.” 28 U.S.C. § 1491(b)(1).

In a 2025 decision, Telesto Group, LLC v. United States, the Court held that challenges to an agency’s conduct of the prototyping phase of an OT fall outside of COFC’s protest jurisdiction until prototyping concludes and the agency decides to acquire the successful prototype, resulting in an “effective jurisdictional blackout.”  176 Fed. Cl. 711, 733 (2025).  However the Court in Blue Water Autonomy declined to adopt that rationale, explaining that a proposed procurement “begins with the process for determining a need for property or services” and thus “jurisdiction attached . . . before the agency had decided to acquire anything.”  Indeed, the Court, over and over again, characterized the scope of its Tucker Act bid protest jurisdiction as “broad.”

Accordingly, while the Federal Circuit has still not weighed in on the issue, the Blue Water Autonomy decision adds further precedent on the side of COFC’s ability to exercise jurisdiction over certain OT protests.  This is an area to continue to monitor given the Department’s recent and well-documented push to increase the use of OT’s instead of traditional procurement contracts.

“The Court finds that its broad procurement protest statute, 28 U.S.C. § 1491(b)(1), encompasses the instant protest because the OT competition at issue is in connection with the Navy’s procurement of MUSVs,” Judge Philip Hadji wrote in a legal opinion filed today. “Accordingly, the Government’s Motion to Dismiss is DENIED.”